FERC Order 1000 Competitively Bid Transmission Projects​

2021 – 2025 Ratepayer Savings & Benefits

FERC Order 1000 Competitively Bid Transmission Projects​​

2021 – 2025 Ratepayer Savings & Benefits

Examples of Transmission Projects that Were Competitively Bid

Includes Cost Overrun Protections & Schedule Guarantees

  • Region: MISO
  • RTO / ISO Estimate ($MM): $662
  • Winning Bid Cost ($MM):$349
  • Cost Savings ($MM): $313
  • Competitive Discount: 47%
  • Cost Containment Offered on Winning Bid: Yes
  • Schedule Guarantee Offered on Winning Bid: Yes
  • Region: MISO
  • RTO / ISO Estimate ($MM): $2,327
  • Winning Bid Cost ($MM): $1,165
  • Cost Savings ($MM): $1,162
  • Competitive Discount: 50%
  • Cost Containment Offered on Winning Bid: Yes
  • Schedule Guarantee Offered on Winning Bid: Yes
  • Region: MISO
  • RTO / ISO Estimate ($MM): $254
  • Winning Bid Cost ($MM): $77
  • Cost Savings ($MM): $177
  • Competitive Discount: 70%
  • Cost Containment Offered on Winning Bid: Yes
  • Schedule Guarantee Offered on Winning Bid: Yes
*NOTE:
  • All information contained here is based on publicly available information on each respective RTO/ISO Excludes sponsored projects approved by PJM, which do not estimate individual line costs prior to competitive solicitation. ISO-NE and NYISO have not facilitated a competitive transmission RFP in the last five years, excluding offshore wind transmission. Data does not include projects for which the winning bid cost is not publicly disclosed.
  • Table reflects 2021–2025 bid years, representing the period during which competitive solicitation processes had reached sufficient maturity and consistency across RTOs/ISOs to support meaningful
  • Cost containment provisions include Hard Caps, ROE Stepdown Points, and ATRR
  • CAISO estimates show the midpoints of CAISO cost estimate ranges for the competitive portions of
This does not reflect developer performance; all bids received exceeded MISO’s pre-RFP planning estimate, and the winning bid was the lowest proposal submitted.
*Project in service; met or beat need date; ratepayer costs held to cost cap.

RTO/ISO Direct-Assigned Transmission Projects (Non-Competitive)in the FERC Order 1000 Era

No Cost Overrun Protections or Schedule Guarantees

  • Region: PJM
  • Awarded Utility: BGE/PECO/Exelon
  • Original Cost ($MM): $739
  • Latest/Final Cost ($MM): $1,514
  • Cost Increase (%): 105%
  • Region: SPP
  • Awarded Utility: Evergy
  • Original Cost ($MM): $48
  • Latest/Final Cost ($MM): $73
  • Cost Increase (%): 52%
  • Region: ISO-NE
  • Awarded Utility: Eversource
  • Original Cost ($MM): $213
  • Latest/Final Cost ($MM): $317
  • Cost Increase (%): 49%
*NOTE:
  • All information contained here is based on publicly available information on each respective RTO/ISO website, and contains in service or late-stage projects or projects with cost data approved for construction between 2012 and
  • MISO MVP project with both direct-assigned (non-competitive) and competitive Competitive scope and cost was removed so that only direct-assigned scope and cost is shown.
  • MISO MVP project with a cost change (cost increase) that is under Variance Analysis
* Project in service.
/ SIGN UP

The Federal Energy Regulatory Commission Must Protect Consumers Over Utility Profits.

Join the Electricity Transmission Competition Coalition mailing list and stay up to date on the latest federal and local conversations on transmission competition: