FERC Order 1000 Competitively Bid Transmission Projects​

2021 – 2025 Ratepayer Savings & Benefits

FERC Order 1000 Competitively Bid Transmission Projects​​

2021 – 2025 Ratepayer Savings & Benefits

Examples of Transmission Projects that Were Competitively Bid

Includes Cost Overrun Protections & Schedule Guarantees

  • Region: MISO
  • RTO / ISO Estimate ($MM): $662
  • Winning Bid Cost ($MM):$349
  • Cost Savings ($MM): $313
  • Competitive Discount: 47%
  • Cost Containment Offered on Winning Bid: Yes
  • Schedule Guarantee Offered on Winning Bid: Yes
  • Region: MISO
  • RTO / ISO Estimate ($MM): $2,327
  • Winning Bid Cost ($MM): $1,165
  • Cost Savings ($MM): $1,162
  • Competitive Discount: 50%
  • Cost Containment Offered on Winning Bid: Yes
  • Schedule Guarantee Offered on Winning Bid: Yes
  • Region: MISO
  • RTO / ISO Estimate ($MM): $254
  • Winning Bid Cost ($MM): $77
  • Cost Savings ($MM): $177
  • Competitive Discount: 70%
  • Cost Containment Offered on Winning Bid: Yes
  • Schedule Guarantee Offered on Winning Bid: Yes
*NOTE:
  • All information contained here is based on publicly available information on each respective RTO/ISO Excludes sponsored projects approved by PJM, which do not estimate individual line costs prior to competitive solicitation. ISO-NE and NYISO have not facilitated a competitive transmission RFP in the last five years, excluding offshore wind transmission. Data does not include projects for which the winning bid cost is not publicly disclosed.
  • Table reflects 2021–2025 bid years, representing the period during which competitive solicitation processes had reached sufficient maturity and consistency across RTOs/ISOs to support meaningful
  • Cost containment provisions include Hard Caps, ROE Stepdown Points, and ATRR
  • CAISO estimates show the midpoints of CAISO cost estimate ranges for the competitive portions of
This does not reflect developer performance; all bids received exceeded MISO’s pre-RFP planning estimate, and the winning bid was the lowest proposal submitted.
*Project in service; met or beat need date; ratepayer costs held to cost cap.

RTO/ISO Direct-Assigned Transmission Projects (Non-Competitive)in the FERC Order 1000 Era

No Cost Overrun Protections or Schedule Guarantees

  • Region: PJM
  • Awarded Utility: BGE/PECO/Exelon
  • Original Cost ($MM): $739
  • Latest/Final Cost ($MM): $1,514
  • Cost Increase (%): 105%
  • Region: SPP
  • Awarded Utility: Evergy
  • Original Cost ($MM): $48
  • Latest/Final Cost ($MM): $73
  • Cost Increase (%): 52%
  • Region: ISO-NE
  • Awarded Utility: Eversource
  • Original Cost ($MM): $213
  • Latest/Final Cost ($MM): $317
  • Cost Increase (%): 49%
*NOTE:
  • All information contained here is based on publicly available information on each respective RTO/ISO website, and contains in service or late-stage projects or projects with cost data approved for construction between 2012 and
  • MISO MVP project with both direct-assigned (non-competitive) and competitive Competitive scope and cost was removed so that only direct-assigned scope and cost is shown.
  • MISO MVP project with a cost change (cost increase) that is under Variance Analysis
* Project in service.
/ DOWNLOAD

FERC’S $277 BILLION ELECTRICITY PRICE HIKE

Read How the Federal Energy Regulatory Commission’s Failure to Enforce Transmission Competition Will Lead to Decades of Electricity Price Inflation for American Consumers.